Question: Consider a simple process where work flows from Activity A to Activity B to Activity C to Activity D. Activity A takes 3 minutes and
Consider a simple process where work flows from Activity A to Activity B to Activity C to Activity D. Activity A takes 3 minutes and is performed by Aaron. Activity B takes 5 minutes and is performed by Aaron and Betty together. Activity C takes 4 minutes and is performed by Betty and David. Activity D is performed by David and takes 3 minutes. What is the bottleneck of the process?
Group of answer choices
Activity A
None of these
Activity C
Activity B
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
