Question: Consider a simple project of three sequential activities that are sequenced with the following project network diagram: [A]-[B]-[C].True or false? Activity A is an immediate
Consider a simple project of three sequential activities that are sequenced with the following project network diagram: [A]-[B]-[C].True or false? Activity A is an immediate predecessor of activity C.