Question: QUESTION 8 Consider a simple project of three sequential activities that are sequenced with the following project network diagram: [A] [B] [C] . True or

QUESTION 8 Consider a simple project of three

QUESTION 8 Consider a simple project of three sequential activities that are sequenced with the following project network diagram: [A] [B] [C] . True or false? Activity A is an immediate predecessor of activity C. O True O False