Question: Consider a simple project that involves 2 tasks A and B that can be done in parallel. The project is complete when both tasks A

Consider a simple project that involves 2 tasks A

Consider a simple project that involves 2 tasks A and B that can be done in parallel. The project is complete when both tasks A and B are complete. Let ta denote the time to complete task A. Let to denote the time to complete task B What is the project completion time? Select one: O a. takto b. min(tats) O c. ta + tb d. max(ta,te)