Question: Consider a two - station serial production line. The rst station consists of a single machine with a mean processing time of 3 hours and
Consider a twostation serial production line. The rst station consists of a single
machine with a mean processing time of hours and a standard deviation of hours. At the
second station, there are two identical machines, each with a mean and standard deviation
of hours and hours, respectively, for the processing time.
a pts What is the highest arrival rate that this system can handle?
b pts Using analytical approximations, calculate the average cycle time for the system
assuming that the interarrival process is exponential with a rate of : jobshour
c pts Suppose the two machines in the second station is replaced by a single machine
that is twice faster such that the mean process time is : hours. Assume that the
standard deviation stays the same. How will the CT change? Show your calculations
clearly. Compare the cycle times in parts b and c and explain the reasons for the
dierence.
d Suppose that the production line in part b is reversed so that station replaces
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock