Question: Consider a two-station line with single-machine stations. The average processing times on stations 1 and 2 are 15 and 12 minutes, respectively. There are no

Consider a two-station line with single-machine stations. The average processing times on stations 1 and 2 are 15 and 12 minutes, respectively. There are no setups or breakdowns at the machines. What is the critical WIP (W_0) for the line