Question: Consider an assembly line with 3 sequential operations A, B, and C with processing times per part of 10, 20, and 40 minutes, respectively. Each
Consider an assembly line with 3 sequential operations A, B, and C with processing times per part of 10, 20, and 40 minutes, respectively. Each operation has a dedicated worker. The bottleneck operation is:
A) A
B) B
C) C