Question: Consider an assembly line with 3 sequential operations A , B , and C with processing rates 1 0 , 4 0 , and 3

Consider an assembly line with 3 sequential operations A, B, and C with processing rates 10,40, and 30 parts per hour, respectively. Suppose there is one dedicated worker for A and B (Abe) and one dedicated worker for C (Chris). Suggest a way of reassigning tasks to Abe and Chris so as to maximize the process capacity. What is the maximum process capacity?