Question: Consider an E 2 / M / 1 / 4 model with the arrival rate of 3 jobs per hour and a service rate of

Consider an E2/M/1/4 model with the arrival rate of 3 jobs per hour and
a service rate of 4 jobs per hour. Compute the steady state probabilities and the
system performance measures of utilization, CTs, WIPs, and throughput. Note that
this system has a capacity of 4 jobs.