Question: consider below the following project and its activities, normal time, and crashing cost per day. crash the project so that the expected project duration time
consider below the following project and its activities, normal time, and crashing cost per day. crash the project so that the expected project duration time is 8 days and the crash cost is minimized. which activities are crashed, and what are their completion times?
| activities | predecessor | Project normal time | Project shortest time | Crash cost per day |
| A | - | 3 days | 1 | 5 |
| B | - | 4 | 2 | 4 |
| C | A | 5 | 3 | 3 |
| D | A.B | 6 | 4 | 2 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
