Question: Consider the 7 activities of a project, whose precedences, execution time and costs appear in the following table: Activity Preceded by Normal time (days) Normal
Consider the 7 activities of a project, whose precedences, execution time and costs appear in the following table:
| Activity | Preceded by | Normal time (days) | Normal Cost ($ per day) | Accelerated time (days) | Accelerated cost ($ per day) |
| A | - | 10 | 2000 | 8 | 2400 |
| B | - | 12 | 1500 | 10 | 1800 |
| C | - | 13 | 700 | 11 | 850 |
| D | A,B | 14 | 5600 | 13 | 5650 |
| E | B | 13 | 1600 | 10 | 2200 |
| F | D,E | 5 | 2500 | 4 | 2600 |
| G | B,C | 10 | 1000 | 8 | 1050 |
a) Determine the critical path(s) and the execution time of the project. b) Calculate the cost slopes of each project activity. c) How much will it cost to advance the execution time of the work by 3 days? d) Make the graph TIME - COST.