Question: Consider the batch flow process A then b then c. A processing time = 5 minutes, B processing time = 3 minutes, C processing time

Consider the batch flow process A then b then c. A processing time = 5 minutes, B processing time = 3 minutes, C processing time = 6 minutes Each of the 3 operations A, B, and C operates on individual parts. A has a set up time of 20 mins. B and C do not have any set up time. Calculate the recommended batch size.