Question: Consider the below table for a project with its given network diagram as below. Activity Immediate Predecessors Time (weeks) A --- 3 B --- 4
Consider the below table for a project with its given network diagram as below.
| Activity | Immediate Predecessors | Time (weeks) |
| A | --- | 3 |
| B | --- | 4 |
| C | --- | 2 |
| D | A | 4 |
| E | A, B | 5 |
| F | A, B, C | 2 |
| G | D, E, H | 1 |
| H | E, F | 6 |
Complete the network diagram below by finding the ES, EF, LS, LF, and Slack times, then calculate the total usable slack time without delaying the total project duration.