Question: Consider the below table for a project with its given network diagram as below. Activity Immediate Predecessors Time (weeks) A --- 3 B --- 4

Consider the below table for a project with its given network diagram as below.

Activity

Immediate Predecessors

Time (weeks)

A

---

3

B

---

4

C

---

2

D

A

4

E

A, B

5

F

A, B, C

2

G

D, E, H

1

H

E, F

6

Complete the network diagram below by finding the ES, EF, LS, LF, and Slack times, then calculate the total usable slack time without delaying the total project duration.