Question: Roger Ginde is developing a program in supply chain management certification for mangers. Ginde has listed a number of activities that must be completed before

Roger Ginde is developing a program in supply chain management certification for mangers.
Ginde has listed a number of activities that must be completed before a training program of this
nature could be conducted. The activities, immediate predecessors, and times appear in the
accompanying table. Please show your work.
Activity Immediate
Predecessor(s)
Time
(weeks)
A None 2
B None 5
C None 1
D B 10
E A, D 3
F C 6
G E, F 8
3.13. The following represent activities in Marc Masouds Construction Company project
Activity Immediate
Predecessor(s)
Time
(weeks)
A None 1
B None 4
C A 1
D B 5
E B 2
F C, E 7
G D 2
H F, G 3
a) Drawe the network to represent his situation.
b) What activities are on the critical path? Please show your work.
c) What is the length of the critical path? Please show your work.
3.20. The estimated times and immediate predecessors for the activity in a project at George
Kyariss retinal scanning company are given in the following table. Assume that the activity
times are independent.
Time (weeks)
Activity Immediate
Predecessor(s)
Optimistic
time: a
Most likely
time: m
Pessimistic
time: b
A None 91011
B None 41016
C A 91011
D B 55811

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!