Question: Roger Ginde is developing a program in supply chain management certification for mangers. Ginde has listed a number of activities that must be completed before
Roger Ginde is developing a program in supply chain management certification for mangers.
Ginde has listed a number of activities that must be completed before a training program of this
nature could be conducted. The activities, immediate predecessors, and times appear in the
accompanying table. Please show your work.
Activity Immediate
Predecessors
Time
weeks
A None
B None
C None
D B
E A D
F C
G E F
The following represent activities in Marc Masouds Construction Company project
Activity Immediate
Predecessors
Time
weeks
A None
B None
C A
D B
E B
F C E
G D
H F G
a Drawe the network to represent his situation.
b What activities are on the critical path? Please show your work.
c What is the length of the critical path? Please show your work.
The estimated times and immediate predecessors for the activity in a project at George
Kyariss retinal scanning company are given in the following table. Assume that the activity
times are independent.
Time weeks
Activity Immediate
Predecessors
Optimistic
time: a
Most likely
time: m
Pessimistic
time: b
A None
B None
C A
D B
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock