Question: Consider the crew productivity data shown in the following table. ( 1 5 points ) table [ [ Output , Crew - Hours ]

Consider the crew productivity data shown in the following table. (15 points)
\table[[Output,Crew-Hours],[34,40],[36,42],[47,44],[48,46],[57,48],[59,50],[58,52],[60,54],[59,56],[59,58],[60,60]]
a) Develop a quadratic polynomial model to assess the productivity as a function of overtime hours worked.
b) Does the model fit the data adequately? Why or why not?
c) What is the normal work week (i.e. non-OT) efficiency of this crew?
d) For maximum productivity, what percentage of overtime should be worked?
e) How many hours per week should the crew work?
f) Do you think this level of effort is sustainable over time?
g) Do you think this level of effort safe to work over time? Support your answers.
Consider the crew productivity data shown in the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!