Question: Consider the critical path method example we did in class. How long will this project take if activity B required 5 days to complete, not

Consider the critical path method example we did in class. How long will this project take if activity B required 5 days to complete, not 3?Group of answer choicesNot enough information27 days (We add the additional days to the project duration)26 days (B becomes critical if it takes more than 3 days to complete)25 days (B is not on the critical path)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!