Question: Consider the Data below: Activity Predecessor Duration (Days) A 3 B A 4 A 2 D B 5 E C 1 LL F 2
Consider the Data below: Activity Predecessor Duration (Days) A 3 B A 4 A 2 D B 5 E C 1 LL F 2 G D, E st 4 H F, G 3 A.Construct a PERT network (4 Marks) B.Determine the project duration time (16 Marks) C.Determine the critical path (4 Marks)