Question: Consider the Data below: Activity Predecessor Duration (Days) A 3 B A 4 A 2 D B 5 E C 1 LL F 2

Consider the Data below: Activity Predecessor Duration (Days) A 3 B A 



Consider the Data below: Activity Predecessor Duration (Days) A 3 B A 4 A 2 D B 5 E C 1 LL F 2 G D, E st 4 H F, G 3 A.Construct a PERT network (4 Marks) B.Determine the project duration time (16 Marks) C.Determine the critical path (4 Marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!