Question: Consider the project information in the table (time in weeks) Activity Immediate Predecessor E b A 5 10 15 B A 11 15 19

Consider the project information in the table (time in weeks) Activity Immediate 





Consider the project information in the table (time in weeks) Activity Immediate Predecessor E b A 5 10 15 B A 11 15 19 A 13 17 21 D B, C 14 16 21 E 8 18 22 F G D 9 13 17 E, F 6 11 16 a. Construct the PERT network diagram for this project. b. Compute the mean and variance in time for each activity c. Find the critical path and determine the expected length of the critical path? d. Assuming normality and path independence, what is the probability of meeting the 72-week deadline?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!