Question: Consider the dependency matrix and the activity durations provided below. Downstream Activity Upstream Activity 1 2 3 4 5 6 7 8 9 10 1
Consider the dependency matrix and the activity durations provided below.
| Downstream Activity | Upstream Activity | ||||||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | ||
| 1 | |||||||||||
| 2 | X | ||||||||||
| 3 | X | ||||||||||
| 4 | X | ||||||||||
| 5 | X | ||||||||||
| 6 | X | ||||||||||
| 7 | X | ||||||||||
| 8 | X | ||||||||||
| 9 | X | X | |||||||||
| 10 | X | X | |||||||||
| Activity | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
| Time | 11 | 10 | 14 | 11 | 1 | 18 | 10 | 13 | 12 | 2 |
a. Which of the following graphs visually depict the evolution of this project.
Option 1:
Option 2:
Option 3:
Option 4:
b. Find the critical path.
c. For each activity, compute the late start, the late completion, and the slack time.
rev: 10_31_2019_QC_CS-188125, 02_06_2020_QC_CS-199320
This is the last question in the assignment. To submit, use Alt + S. To access other questions, proceed to the question map button.N
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
