Question: Consider the following: Activity Normal time Predecessor A 4 --- B 8 --- C 4 --- D 2 A E 3 C What is the
Consider the following:
| Activity | Normal time | Predecessor |
| A | 4 | --- |
| B | 8 | --- |
| C | 4 | --- |
| D | 2 | A |
| E | 3 | C |
What is the project's completion time?