Question: Consider the following: Activity Normal time Predecessor A 4 --- B 8 --- C 4 --- D 2 A E 3 C What is the

Consider the following:

Activity Normal time Predecessor
A 4 ---
B 8 ---
C 4 ---
D 2 A
E 3 C

What is the project's completion time?