Question: Consider the following project: Activity Time Predecessor A 1 2 - B 1 0 - C 9 A D 1 5 A E 7 B
Consider the following project:
Activity Time Predecessor
A
B
C A
D A
E B
F D E
G C F
What is the fastest this project can be completed?