Question: Consider the following Activity-On-Node (AON) PERT project. The three values that represent each activity's completion time (in days) correspond to an optimistic time, most likely
Consider the following Activity-On-Node (AON) PERT project. The three values that represent each activity's completion time (in days) correspond to an optimistic time, most likely time, and pessimistic time, respectively. What is the probability of completing the project within 18 days? Click here to view a Word version of the project. Question 4 options: 0.0668 0.0612 0.0733 0.0795
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer