Question: Consider the following Activity-On-Node Network: Start 17 16 What is the earliest completion time for the project? O 14 B 7 15 A 3
Consider the following Activity-On-Node Network: Start 17 16 What is the earliest completion time for the project? O 14 B 7 15 A 3 C 2 D 7 E 1 F 2 G 1