Question: Consider the following batch flow process consisting of three process steps performed by three machines: Activ Setur Work is processed in batches at each step.
Consider the following batch flow process consisting of three process steps performed by three machines:
Activ
Setur
Work is processed in batches at each step. Before a batch is processed at step the machine has to be set up During a setup, the machine is unable to process any product.
a Assume that the batch size is parts. What is the capacity of the process?
b For a batch size of parts, which step is the bottleneck for the process?
c Using the current production batch size of parts, how long would it take to produce parts starting with an empty system? Assume that the units in the batch have to stay together no smaller transfer batches allowed when transferred to step and to step A unit can leave the system the moment it is completed at step Assume step needs to be set up before the beginning of production.
d Using the current production batch size of parts, how long would it take to produce parts starting with an empty system? Assume that the units in the batch do not have to stay together; specifically, units are transferred to the next step the moment they are completed at any step. Assume step needs to be set up before the beginning of production.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock