Question: Consider the following data: Activity Preceding Activity Start Su Estimate in Months 0 D Start 6 A Start 8 LL F D,A 10 E
Consider the following data: Activity Preceding Activity Start Su Estimate in Months 0 D Start 6 A Start 8 LL F D,A 10 E D 14 0 F,E 7 B F 8 H G 9 C H 11 End C,B 49 0 1. What is the critical path? 2. What is the duration of the critical path? 3. What is the float of activity B? 4. What is the float of activity E? 5. What is the float of activity D? 6. To shorten the length of the project, the sponsor has offered to remove the work of activity E from the project, making activity D the predecessor to activities G and F. What will be the effect?