Question: Consider the following data: Activity Preceding Activity Start Su Estimate in Months 0 D Start 6 A Start 8 LL F D,A 10 E

Consider the following data: Activity Preceding Activity Start Su Estimate in Months

Consider the following data: Activity Preceding Activity Start Su Estimate in Months 0 D Start 6 A Start 8 LL F D,A 10 E D 14 0 F,E 7 B F 8 H G 9 C H 11 End C,B 49 0 1. What is the critical path? 2. What is the duration of the critical path? 3. What is the float of activity B? 4. What is the float of activity E? 5. What is the float of activity D? 6. To shorten the length of the project, the sponsor has offered to remove the work of activity E from the project, making activity D the predecessor to activities G and F. What will be the effect?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!