Question: Consider the following data for a project to install a new server at the Northland Pines High School: table [ [ Activity , Activity

Consider the following data for a project to install a new server at the Northland Pines High School:
\table[[Activity,Activity Time (days),Immediate Predecessor(s)],[A,4,-],[B,5,A],[C,4,A],[D,4,B],[E,1,B],[F,9,B, C],[G,2,D, E],[H,6,F],[I,3,F],[J,8,G, H, I]]
a. Choose the correct network diagram below.
a. Choose the correct network diagram below.
A.
B
c.
10??
b. Calculate the critical path for this project.
The critical path is A-B-F-H-J and the project duration is 32 days. (Enter your response as a whole number.)
c. How much slack is in each of the activities G, H, and I?
\table[[Activity,\table[[Activity],[Time (days)]],\table[[On],[critical path?]],\table[[Slack],[(days)]]],[G,2,No,
 Consider the following data for a project to install a new

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!