Question: Consider the following data for a project to install a new server at the Northland Pines High School: Activity Activity Time (days) Immediate Predecessor(s) Task
Consider the following data for a project to install a new server at the Northland Pines High School:
| Activity | Activity Time (days) | Immediate Predecessor(s) |
| Task A | 2 | - |
| Task B | 4 | A |
| Task C | 1 | A |
| Task D | 2 | B |
| Task E | 6 | B |
| Task F | 8 | B, C |
| Task G | 3 | D, E |
| Task H | 5 | F |
| Task I | 4 | C, F |
| Task J | 5 | G, H, I |
For the project to install a new server at the Northland Pines High School, what is the latest start (LS) time for Activity C?
Select one:
a. 2 days
b. 3 days
c. 5 days
d. 6 days
e. None of the above
For the project to install a new server at the Northland Pines High School, what is the slack for Activity D?
Select one:
a. 0 days
b. 1 days
c. 3 days
d. 8 days
e. None of the above
For the project to install a new server at the Northland Pines High School, what is the slack for Activity E?
Select one:
a. 2 days
b. 3 days
c. 4 days
d. 5 days
e. None of the above
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts