Question: Consider the following data for a project to install a new server at the Northland Pines High School: Activity Activity Time (days) Immediate Predecessor(s) Task
Consider the following data for a project to install a new server at the Northland Pines High School:
| Activity | Activity Time (days) | Immediate Predecessor(s) |
| Task A | 2 | - |
| Task B | 4 | A |
| Task C | 1 | A |
| Task D | 2 | B |
| Task E | 6 | B |
| Task F | 8 | B, C |
| Task G | 3 | D, E |
| Task H | 5 | F |
| Task I | 4 | C, F |
| Task J | 5 | G, H, I |
How many paths exist for the project to install a new server at the Northland Pines High School?
Select one:
a. 6
b. 7
c. 5
d. 8
e. None of the above
What is the critical path for the project to install a new server at the Northland Pines High School?
Select one:
a. ABEGJ
b. ABFHJ
c. ABFIJ
d. ACFHJ
e. None of the above
What is the length of the critical path for the project to install a new server at the Northland Pines High School?
Select one:
a. 23 days
b. 24 days
c. 25 days
d. 27 days
e. None of the above