Question: Consider the following data for a project to install a new server at the Northland Pines High School: a. Draw the network diagram. b. Calculate

Consider the following data for a project to

Consider the following data for a project to install a new server at the Northland Pines High School: a. Draw the network diagram. b. Calculate the critical path for this project. C. How much slack is in each of the activities G, H, and I? Immediate Predecessor(s) Activity B Activity Time (days) 2 4 A C 5 A D 2 B E 1 B F 8 B, C 3 DE G H 5 F 1 4 F J 7 G, H.1