Question: Consider the following data for a project to install a new server at the Northland Pines High School Activity Activity Time (days) Immediate Predecessor(s) A

Consider the following data for a project to install a new server at the Northland Pines High School

Activity Activity Time (days) Immediate Predecessor(s)
A 2 ---
B 4 A
C 5 A
D 2 B
E 1 B
F 8 B, C
G 3 D, E
H 5 F
I 4 F
J 7 G, H, I

a. Draw the network diagram

b. Calculate the critical path for this project

c. How much slack is in each of the activities G,H, and I?

**Must show work**

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!