Question: Consider the following data for a project to install a new server at the Northland Pines High School Activity Activity Time (days) Immediate Predecessor(s) A
Consider the following data for a project to install a new server at the Northland Pines High School
| Activity | Activity Time (days) | Immediate Predecessor(s) |
|---|---|---|
| A | 2 | --- |
| B | 4 | A |
| C | 5 | A |
| D | 2 | B |
| E | 1 | B |
| F | 8 | B, C |
| G | 3 | D, E |
| H | 5 | F |
| I | 4 | F |
| J | 7 | G, H, I |
a. Draw the network diagram
b. Calculate the critical path for this project
c. How much slack is in each of the activities G,H, and I?
**Must show work**