Question: Consider the following data for another project What is the probability that the project will be done in 28 days or less ? Assuming each

Consider the following data for another project

 Consider the following data for another project What is the probability

What is the probability that the project will be done in 28 days or less?

Assuming each activity can be crashed at least two days, what is the cost to reduce the expected project duration by 2 days? Which activities would be crashed?

\begin{tabular}{|c|c|c|c|c|} \hline Activity & Predecessor & t & 2 & Crash Costiday, \\ \hline A & - & 11 & 2 & 6 \\ \hline B & - & 7 & 1.5 & 5 \\ \hline C & - & 12 & 2 & 10 \\ \hline D & A.B & 5 & 1.5 & 15 \\ \hline E & C & 15 & 0.1 & 12 \\ \hline F & D & 10 & 2.5 & 16 \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!