Question: Consider the following four-step process: each product needs to go through activities A, B, C, D sequentially. There are 4 types of workers (A, B,
Consider the following four-step process: each product needs to go through activities A, B, C, D sequentially. There are 4 types of workers (A, B, C, D), who are responsible for the 4 activities, respectively. The process time required for each activity and the number of workers for each type are given in the following table. For example, there are 2 Type A workers, and each of them spends 0.25 minutes to process a unit during activity A.
The following data are available for the four steps:
Suppose the steps in activity D can be done easier with new approach, and the activity time is reduced by 50% (i.e., reduced to 0.25 min per unit) now. Assume everything else remains the same, what is the capacity of the process? Choose the closest number if needed.
8 units/minute
12 units/minute
16 units/minute
10 units/minute
9 units/minute