Consider the following information: Task Task Length (days) Predecessors 1 2. 2 5 1 3 3 3 1 4 4 2 5 1 2 6 4 3 7 3 4 8 2 9 9 5 6,7,8 10 1 9 What will be the value of the latest start for task 8