Question: A Moving to the next question prevents changes to this answer Question 25 Consider the following project: Task ID Duration (Days) Predecessors 2 70 3

A Moving to the next question prevents changes to

A Moving to the next question prevents changes to this answer Question 25 Consider the following project: Task ID Duration (Days) Predecessors 2 70 3 30 2 4 5 2 6 7 8 9 120 120 120 120 150 115 130 90 30 120 75 30 85 5 3,6 3,6 3,6 7,9 7,9 79 7.9 10 11 13 14 15 10 14 16 6 17 16 18 16 165 90 90 20 19 20 17,18 8,11,13,15,19 What is the slack for task 8? O 115 0 145 O 205 O 225 > A Moving to the next question prevents changes to this

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!