Question: Consider the following network for conducting a 2 - week ( 1 0 working days ) computer training class: A 2 B 1 7 3
Consider the following network for conducting a week working days computer training class:
AB
E CD
a Construct a schedule showing: ESs for all activities
LSs for all activities
Slacks for all activities Critical path