Question: Consider the following network. I. ( 1 0 points ) What is the original critical path? What is the original project duration? II . (

Consider the following network.
I. (10 points) What is the original critical path? What is the original project duration?
II.(15 points) Modify the network using the critical chain approach. Assume no resource information is available. Please show the successive configurations in transitioning from the original schedule to the critical chain network (for examples, see sample problem on Blackboard
and pages 335-336 in CCPM-Pinto-Chap11.pdf).
III. (10 points) What is the new duration of the project? How long are the project and feeder buffers?