Question: Immediate Activity Predecessors A m b E B, C 4 6 8 F B 6 7 8 G D, E 1 2 6 H

Immediate Activity Predecessors A m b E B, C 4 6 8 F B 6 7 8 G D, E 1 2 6 H F, G 4 6 16 a. Draw a network for this project and determine the critical path based on the most likely times by inspection. b. Assuming that the critical path is the one you identified in part (a), what is the proba- bility that the project will be completed before 28 weeks? Before 32 weeks? c. Assuming that the critical path is the one you identified in part (a), how many weeks are required to complete the project with probability.95?
Step by Step Solution
There are 3 Steps involved in it
To address all parts of this question lets proceed step by step Part a Draw a Network for This Project and Determine the Critical Path Based on the Most Likely Times by Inspection Given Data Activity ... View full answer