Question: Activity Predecessor Optimistic O Most likely M Pessimistic b A - 5 8 17 B - 7 10 13 C A 3 5 7 D
| Activity | Predecessor | Optimistic O | Most likely M | Pessimistic b |
| A | - | 5 | 8 | 17 |
| B | - | 7 | 10 | 13 |
| C | A | 3 | 5 | 7 |
| D | A | 1 | 3 | 5 |
| E | A, C | 4 | 6 | 8 |
| F | B, C | 3 | 3 | 3 |
| G | D, E | 3 | 4 | 5 |
By using evaluating and reviewing the project (PERT) ?
- What is the expected time to finish the project? And the project completion time variation?
- If the contractor is liable to pay a penalty of $ 300,000 if the implementation of the project is delayed for more than a month from the expected completion time of the project, then what is the likelihood that the contractor will be obligated to pay the penalty?