Question: Consider the following processing times and due dates for four jobs: Processing Job # Time Due Date 1 15 2 23 23 3 11 36

Consider the following processing times and due
Consider the following processing times and due dates for four jobs: Processing Job # Time Due Date 1 15 2 23 23 3 11 36 4 8 47 56 Calculate the mean flow time based on shortest processing time rule. O a. 29.5 O b. 8.5 O c. 39 d. 0.25