Question: Consider the following project activities with a normal unit: ( The normal unit is Day ) Activity Name Immediate Predecessor (list number/ name, separated by
Consider the following project activities with a normal unit:
(The normal unit is Day)
| Activity Name | Immediate Predecessor (list number/ name, separated by ,) | Normal Time |
| A |
| 6 |
| B | A | 2 |
| C | A | 4 |
| D | B, C | 3 |
| E | D | 1 |
| F | D | 7 |
| G | E | 4 |
| H | F, G | 2 |
| I | F | 6 |
| J | I | 1 |
| K | H, J | 5 |
Fill the following table:
| Activity Name | Activity Time | Earliest Expected Competition Time (TE) | Latest Expected Competition Time (TL) | Slack (TL-TE) |
| A | 6 |
|
|
|
| B | 2 |
|
|
|
| C | 4 |
|
|
|
| D | 3 |
|
|
|
| E | 1 |
|
|
|
| F | 7 |
|
|
|
| G | 4 |
|
|
|
| H | 2 |
|
|
|
| I | 6 |
|
|
|
| J | 1 |
|
|
|
| K | 5 |
|
|
|
| Project Completion Time = |
| Days | ||
| The Critical Path is= |
| |||