Question: Consider the following project: Activity A , Duration 3 , Predecessor None Activity B , Duration 6 days, Predecessor A Activity C , Duration 3

Consider the following project:
Activity A, Duration 3, Predecessor None
Activity B, Duration 6 days, Predecessor A
Activity C, Duration 3 days, Predecessor A
Activity D, Duration 3 days, Predecessors B, C
Activity E, Duration 4 days, Predecessor D
Activity F, Duration 6 days, Predecessor D
What is the slack for activity B?
Question 6Select one:
a.
None of these answers is correct
b.
2 days
c.
6 days
d.
3 days
e.
0 days

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!