Question: Consider the following project: Activity A , Duration 3 , Predecessor None Activity B , Duration 6 days, Predecessor A Activity C , Duration 3
Consider the following project:
Activity A Duration Predecessor None
Activity B Duration days, Predecessor A
Activity C Duration days, Predecessor A
Activity D Duration days, Predecessors B C
Activity E Duration days, Predecessor D
Activity F Duration days, Predecessor D
What is the slack for activity B
Question Select one:
a
None of these answers is correct
b
days
c
days
d
days
e
days