Question: Consider the following project Activity Optimistic (a) Pessimistic (b) Most Likely (m) Predecessors A 1 3 2 - B 2 4 3 - C 4
Consider the following project
| Activity | Optimistic (a) | Pessimistic (b) | Most Likely (m) | Predecessors |
| A | 1 | 3 | 2 | - |
| B | 2 | 4 | 3 | - |
| C | 4 | 6 | 5 | A |
| D | 8 | 10 | 9 | B |
| E | 2 | 8 | 5 | C,D |
| F | 4 | 6 | 5 | D |
| G | 1 | 3 | 2 | E |
Hint: use the most likely time as your activity durations
Question: what is the probability that the project will finish on or before 20 week?
Instructions: show all your calculations, activity times are in weeks
Note: this question is coming from Project Management "A Multi-Disciplinary Approch