Question: Consider the following project: Immed. Optimistic Most Likely Pessimistic Activity Predec. Time (Hr.) Time (Hr.) Time (Hr.) A -- 2 4 6 B A 1
Consider the following project:
Immed. Optimistic Most Likely Pessimistic
Activity Predec. Time (Hr.) Time (Hr.) Time (Hr.)
A -- 2 4 6
B A 1 7 5
C A 3 3 2
D A,B 4 5 9
E C 0.5 1 1.5
F C,D 2 3 6
A) Draw or explain the network or explain the precedences (5 Marks)
B) Calculate the expected time for each activity (5 Marks)
C) Calculate the variance for each activity (5 Marks)