Question: Consider the following project: Activity Predecessor Activity Duration Estimate (days) A - 2 B A 2 C A 3 D A 4 E B 2
Consider the following project:
| Activity | Predecessor Activity | Duration Estimate (days) |
| A | - | 2 |
| B | A | 2 |
| C | A | 3 |
| D | A | 4 |
| E | B | 2 |
| F | C | 3 |
| G | D | 6 |
| H | E, F | 2 |
| I | E, F | 5 |
| J | G, I | 1 |
| K | H, J | 2 |
1. Create a GANTT Chart using the grid on the next page. Make sure to label axis, and provide a title.
2. Create an AON network diagram as discussed in class showing ES, EF, LS, LF.
3. What is the critical path for this project and how long is it?
4. What is the shortest possible time it will take to complete this project?
5. What would happen if activity H were revised to take six days instead of two days?