Question: Consider the following project. Activity Resources Immediate Duration Predecessor (days) 2 A X, Y B A A B, C D Uw u U nnmm X

Consider the following project. Activity

Consider the following project. Activity Resources Immediate Duration Predecessor (days) 2 A X, Y B A A B, C D Uw u U nnmm X Y F. D 1 W, X W, X, Y X, Y G E, F 2 Requirements: a) Draw a Gantt chart b) Find the critical path and project duration in days c) Prepare a Resource chart for Resource X d) Level the resource X and determine the new project duration and critical path