Question: Consider the following project. Activity Predecessor(s) Duration (days) A -- 6.3 B A 2.2 C A 2.4 D C 4.2 E C 2.9 F B

Consider the following project.

Activity Predecessor(s) Duration (days)
A -- 6.3
B A 2.2
C A 2.4
D C 4.2
E C 2.9
F B 3.4
G D, F 4.0
H D, E 3.2
I G, H 2.6

What is the project duration?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!