Question: Solve for the following requirements based on the data given below ACTIVITY PREDECESSOR DURATION (DAYS) A - 5 B A 2 C A 12 D

Solve for the following requirements based on the data given below

ACTIVITY PREDECESSOR DURATION (DAYS)
A - 5
B A 2
C A 12
D - 3
E B 5
F D 1
G B 7
H E,C 2
I G,F 10
J H,I 6

What is the early start of activity C? [ Select ] ["15", "0", "5", "10"]

What is the early finish of activity H? [ Select ] ["19", "14", "12", "24"]

What is the late start of activity I? [ Select ] ["22", "14", "19", "10"]

What is the late finish of activity F? [ Select ] ["14", "13", "22", "17"]

What is the early finish of activity E? [ Select ] ["22", "7", "12", "17"]

What is the slack time of activity D? [ Select ] ["5", "15", "0", "10"]

What is the slack time of activity A? [ Select ] ["15", "10", "5", "0"]

What is the duration until activity F? [ Select ] ["4", "3", "13", "14"]

What is the expected duration of the whole project? [ Select ] ["24", "36", "40", "30"]

What is the critical path of the network? [ Select ] ["A-B-G-I-J", "D-F-I-J", "A-C-H-J", "A-B-E-H-J"]

Previous

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!