Question: Consider the following project. Activity Time (days) A 9 B 6 4 D 6 E 4 B D Finish Start A E Complete the following

Consider the following project. Activity Time

Consider the following project. Activity Time (days) A 9 B 6 4 D 6 E 4 B D Finish Start A E Complete the following table and state the project completion time. Activity ES EF LS LF Slack B D E Project completion time =

Step by Step Solution