Question: Activity Immeadiate Predecessors Durations (weeks) A - 5 B A 3 C A 2 D B 3 E C 7 F B , C 3

Activity Immeadiate Predecessors Durations (weeks) A - 5 B A 3 C A 2 D B 3 E C 7 F B , C 3 G D , E 6 H C 2 What is the latest start time for activity G?

Activity Immeadiate Predecessors Durations

Project management (2) Consider the following project: Activity Immeadiate Predecessors A A B B, C D, E C What is the latest start time for activity G? ABCDEFI G H Durations (weeks) 5 3 2 ~ 3 7 3 6 2