Question: Consider the following project data: ( 8 % ) a ) Construct the PERT network. ( Refer to Question # 2 for the structure to

Consider the following project data: (8%)
a) Construct the PERT network. (Refer to Question
#2 for the structure to use)
b) Indicate the earliest and latest start and finish
times for each activity.
c) Identify the critical path and give the estimated
project completion time.
d) Which activities must not be delayed to ensure
project completion as in (b)?
e) Suppose activity D is delayed four hours. How much is the project delayed?
f) How much slack does activity F have?
Activity Preceding Completion
Times
in hoursActivities
A -3
B A 4
C A 3
D B 3
E C 7
F B,C 3
G D,E 6
H C 2

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!