Question: Consider the following project data: ( 8 % ) a ) Construct the PERT network. ( Refer to Question # 2 for the structure to
Consider the following project data:
a Construct the PERT network. Refer to Question
# for the structure to use
b Indicate the earliest and latest start and finish
times for each activity.
c Identify the critical path and give the estimated
project completion time.
d Which activities must not be delayed to ensure
project completion as in b
e Suppose activity D is delayed four hours. How much is the project delayed?
f How much slack does activity F have?
Activity Preceding Completion
Times
in hoursActivities
A
B A
C A
D B
E C
F BC
G DE
H C